17 February 2022
Site clearance and enabling works have now been completed on our Green Lane project in Blackpool, Cork.
Foundations and retaining walls have progressed to four out of the five blocks, with the rising elements (columns & beams) commenced on two of the blocks.
The Block B, first floor slab installation will be complete in February.
During February and March, we will progress with the concrete frame to each of the five blocks. Boundary retaining wall works will be completed and service diversion works outside the site boundaries will commence.