25 February 2022
Works are progressing well on our Lancaster Gate site in Cork City. The techrete façade at the front of the building was completed prior to the Christmas break. External light guage steel and cement boarding is also progressing steadily.
Window installation to the rear block of the building (Block E) ensures the internal works can progress in parts of the building. 50% of the apartments have first fix internal walls complete with mechanical and electrical works progressing. We are in the process of fitting our precast stairs and half landings.
Over the next couple of months, the majority of the windows and the external façade will be installed. Apartments will start to be completed with commissioning and testing also commencing over this period.