Project Juvederm, AbbVie, Carrogtwohill, Cork
Construction of a two storey steel frame extension to the existing building including demolition of the ground floor to create a new production area.
The works include:
- Building shell & core including demolitions and alterations, piling, structural steel, concrete works, roofing and cladding
- Building fitout including internal partitions, internal wall completions, floor, ceiling & wall finishes, decoration, sanitary fittings and fittings & fixtures
- Site works including site preparation, roads, paths & pavings, surface, foul & process drains, electrical ducting, firemain and process waste sump.
- Site establishment works including contractor carpark & compound, haul road, walkways, temp wheel wash, cabin bases, turnstiles, storm & foul drains, watermain, electrical ducting, fuel
- Storage area and site accommodation.
The project involves working next to and within an existing live production plant and the construction works are phased in such a manner so not to cause interruption to the Fournier ‘business as usual’ activities.